Oracle took another hit after word spread that several data centers tied to its massive OpenAI contract will now finish in 2028, not 2027. Reportedly, the changeOracle took another hit after word spread that several data centers tied to its massive OpenAI contract will now finish in 2028, not 2027. Reportedly, the change

Oracle slides after OpenAI data center delays push timeline to 2028

2025/12/13 01:52

Oracle took another hit after word spread that several data centers tied to its massive OpenAI contract will now finish in 2028, not 2027. Reportedly, the change came from labor shortages and limits on key materials, and investors reacted fast. The stock dropped as much as 6.5%, then traded down 5.3% at $188.26 on Friday.

Oracle and OpenAI did not comment on the delay, even though the projects are meant to support one of the biggest AI infrastructure deals in the world.

The contract is worth $300 billion, signed this summer, and it requires Oracle to supply the computing power to train and run OpenAI’s models.

The US sites are still being built on tight timelines, and people familiar with the work say they are set to become some of the largest data centers on the planet.

Clay Magouyrk, one of Oracle’s chief executives, told investors on an earnings call that the first site in Abilene, Texas, remains on schedule and already has more than 96,000 Nvidia chips delivered. He said, “We have ambitious achievable goals for capacity delivery worldwide.”

Oracle faces pressure as delays trigger market reaction

Oracle’s slide came right after its newest earnings report, which reversed the momentum the company enjoyed earlier this year.

Shares had climbed for months as Oracle locked in multibillion-dollar data center deals, including the OpenAI agreement, and that rally briefly pushed Larry Ellison past Elon Musk as the world’s richest person. That streak ended this week when results landed below analyst expectations and the delays raised new questions about Oracle’s AI push.

Oracle’s cloud business still showed big growth. Fiscal second-quarter cloud revenue jumped 34% to $7.98 billion. Its infrastructure business rose 68% to $4.08 billion, but both numbers came in just under forecasts.

Oracle is now spending heavily on data centers to serve OpenAI, TikTok-owner ByteDance, and Meta. The scale of the build-out has pushed Oracle’s credit costs higher.

ICE Data Services said protecting Oracle’s debt for five years rose as much as 0.17 percentage point to 1.41 percentage point, the highest intraday level since April 2009.

Jacob Bourne, an analyst at Emarketer, said, “Oracle faces its own mounting scrutiny over a debt-fueled data center build-out and concentration risk amid questions over the outcome of AI spending uncertainty.

This revenue miss will likely exacerbate concerns among already cautious investors about its OpenAI deal and its aggressive AI spending.”

Oracle absorbs rising costs as investors look for faster payoff

Oracle’s remaining performance obligation reached $523 billion, well above the $519 billion analysts expected. Investors want to see that flow into revenue sooner rather than later. But Oracle’s cash burn increased this quarter, and free cash flow hit negative $10 billion. Bloomberg data shows the company’s total debt at around $106 billion. JP Morgan’s Mark Murphy wrote, “Investors continually seem to expect incremental cap ex to drive incremental revenue faster than the current reality.”

The delays add another layer of concern for markets still trying to price the risks around Oracle’s AI spending. Workers close to the data center projects said shortages of labor and materials forced the timeline change. These projects were originally meant to showcase Oracle’s ability to move fast in the AI race. Now the shift into 2028 adds pressure on both Oracle and OpenAI.

Clay Magouyrk said in a statement, “Oracle is very good at building and running high-performance and cost-efficient cloud data centers. Because our data centers are highly automated, we can build and run more of them.” The message was meant to reassure investors, but the stock kept falling as traders processed the cost load tied to Oracle’s expansion.

Oracle is trying to hold on to momentum in cloud computing while building some of the most expensive AI sites in the market.

Want your project in front of crypto’s top minds? Feature it in our next industry report, where data meets impact.

Sorumluluk Reddi: Bu sitede yeniden yayınlanan makaleler, halka açık platformlardan alınmıştır ve yalnızca bilgilendirme amaçlıdır. MEXC'nin görüşlerini yansıtmayabilir. Tüm hakları telif sahiplerine aittir. Herhangi bir içeriğin üçüncü taraf haklarını ihlal ettiğini düşünüyorsanız, kaldırılması için lütfen [email protected] ile iletişime geçin. MEXC, içeriğin doğruluğu, eksiksizliği veya güncelliği konusunda hiçbir garanti vermez ve sağlanan bilgilere dayalı olarak alınan herhangi bir eylemden sorumlu değildir. İçerik, finansal, yasal veya diğer profesyonel tavsiye niteliğinde değildir ve MEXC tarafından bir tavsiye veya onay olarak değerlendirilmemelidir.

Ayrıca Şunları da Beğenebilirsiniz

Fed Makes First Rate Cut of the Year, Lowers Rates by 25 Bps

Fed Makes First Rate Cut of the Year, Lowers Rates by 25 Bps

The post Fed Makes First Rate Cut of the Year, Lowers Rates by 25 Bps appeared on BitcoinEthereumNews.com. The Federal Reserve has made its first Fed rate cut this year following today’s FOMC meeting, lowering interest rates by 25 basis points (bps). This comes in line with expectations, while the crypto market awaits Fed Chair Jerome Powell’s speech for guidance on the committee’s stance moving forward. FOMC Makes First Fed Rate Cut This Year With 25 Bps Cut In a press release, the committee announced that it has decided to lower the target range for the federal funds rate by 25 bps from between 4.25% and 4.5% to 4% and 4.25%. This comes in line with expectations as market participants were pricing in a 25 bps cut, as against a 50 bps cut. This marks the first Fed rate cut this year, with the last cut before this coming last year in December. Notably, the Fed also made the first cut last year in September, although it was a 50 bps cut back then. All Fed officials voted in favor of a 25 bps cut except Stephen Miran, who dissented in favor of a 50 bps cut. This rate cut decision comes amid concerns that the labor market may be softening, with recent U.S. jobs data pointing to a weak labor market. The committee noted in the release that job gains have slowed, and that the unemployment rate has edged up but remains low. They added that inflation has moved up and remains somewhat elevated. Fed Chair Jerome Powell had also already signaled at the Jackson Hole Conference that they were likely to lower interest rates with the downside risk in the labor market rising. The committee reiterated this in the release that downside risks to employment have risen. Before the Fed rate cut decision, experts weighed in on whether the FOMC should make a 25 bps cut or…
Paylaş
BitcoinEthereumNews2025/09/18 04:36